Applied Learning on São Paulo’s “University Line”

Scroll

APPLIED LEARNING ON SÃO PAULO’S
“UNIVERSITY LINE”

The Line 6-Orange metro is one of Latin America’s most ambitious rail projects in São Paulo which will soon link the north to the city center, cutting more than an hour off daily commutes.

TACKLING TERRAIN

The new 15-stop route University Line built by Acciona will provide a fast, modern alternative to existing metro and bus options, but constructing the line has been highly complex. To ensure stability, the 15.3 -kilometer double-track tunnel must withstand soft, waterlogged ground and passes under the Tietê River.

Engineers had to tunnel beneath São Paulo’s fluctuating terrain and through varying soil types, including the region’s sticky taguá clay. Reaching over 60 meters deep in some spots, it will become the deepest line in the city and across the continent.

Solving complex tunneling challenges

Advance soil-conditioning solutions by Sika speeds up tunnelling through the shifting local terrain.

Tackling terrain

The new 15-stop route, nicknamed the University Line and built by Acciona, will offer a sleek and speedy alternative to current metro/bus combinations.

BREAKING RECORD WITH SIKA SOLUTIONS

Most of the double-track tunnel was excavated using two tunnel boring machines, each weighing 2,000 tons and 109 meters in length, with a cutting head over 10 meters in diameter.  Despite their power, challenging ground conditions such as abrasive rock, sand, sticky clay, and groundwater required specialized soil conditioning to maintain performance.

Sika developed tailored foaming agents for each ground section and provided continuous on-site technical support, adjusting formulations as conditions changed. This optimized excavation, reduced clogging and downtime, and significantly improved efficiency.

As a result, the average daily rate of excavation increased from the typical 15 to 20 meters of new tunnel to a record 41 meters in 24 hours.

First Challenge

Construction of the continent’s deepest metro station, Itaberaba-Vila Penteado, at 66 meters and nearly twice the depth of the previous record holder.

Second Challenge

Changing soil-conditioning and back-filling needs during the excavation of a double-track tunnel in different types of terrain.

Third Challenge

Complex tunneling under building foundations, utilities infrastructure, metro lines, and the city’s biggest river.

Fourth Challenge

Impact of the dense urban environment and traffic restrictions on construction site logistics, including delivery times and product shelf life.

The construction of Line 6-Orange took teams to new depths to ensure stable, sustainable rail infrastructure deep below São Paulo.

The new metro line has been built under different types of terrain, including the city’s biggest river, the Tietê.

Sika is a vital partner in major urban rail infrastructure projects, including the new Line 6-Orange, or “University Line”, in São Paulo, Brazil.

DURABILITY WITH LOWER ENVIRONMENTAL IMPACT

The tunnel boring machine places curved precast concrete segments behind it which are essential pieces to form the rings that line and reinforce the tunnel. A small gap forms between the soil and the concrete tunnel wall, which is filled with a special grout to keep the tunnel stable. 

Sika Brazil developed a high-performance grout for the required compressive strength — cutting installation time and costs while lowering CO2 emissions.

41 meters

a new one-day tunneling record achieved with Sika solutions

10.6 meters

diameter of the tunnel boring machine’s cutting head

66 meters deep

new station sets a new record

First Sika Solution

Readily biodegradable foaming agents and polymers for soil conditioning

Second Sika Solution

Pre-excavation injections to stabilize the ground before the passage of the TBM

Third Sika Solution

High quality greases and lubricants for TBM main bearing protection and maintenance

Fourth Sika Solution

Tail sealant greases applied between the shield of the TBM and the external surface of the precast concrete tunnel lining to prevent water, excavated ground, and backfill grout from entering the TBM area

Fifth Sika Solution

Backfill grout injected in the annulus ring between the excavated ground and the tunnel lining, with a special emphasis in reducing cement content

Sixth Sika Solution

High-performance admixtures for precast concrete elements

BENEFITS ABOVE GROUND AND BEYOND

Independent studies showed that Sika soil-conditioning solutions kept the excavated soil within low-impact environmental parameters, making it safe to reuse or dispose of. 

Sika teams in Lima (Peru), Santiago (Chile), and São Paulo (for Line 2) are now using the same range of soil-conditioning and backfilling grout solutions on their large-scale urban metro projects.

100+ years

lifespan

15.3 kilometer

double-track tunnel

Cutting

time, water use, CO2 emissions

FUTURE FOCUS

Sika has been a major project partner from the start, providing and although the University Line has yet to open, there are talks of extending it. Sika Brazil is already thinking about implementing new technologies that can accelerate project schedules and introduce other sustainability solutions, according to Michel Haddad, Target Market Manager at Sika Brazil.

The advantage of long-term planning is evident for the hundreds of thousands who will soon enjoy a 23-minute commute instead of spending 90 minutes on public transportation.